In what circumstances must the contractor seek permission from the Department to enter a settlement agreement?
CFR · 2024-01-01 · US · Title 10
The contractor must obtain permission from Department Counsel to enter a settlement agreement if the settlement agreement requires contractor payment of $25,000 or more. Obtaining this approval does not represent a determination that the settlement amount and/or the legal costs incurred in connection with the underlying legal matter will be determined to be allowable.
official document · source cfr-2024 · id 10:§ 719.33