Unreviewed safety question process.
CFR · 2024-01-01 · US · Title 10
(a) The contractor responsible for a Hazard Category 1, 2, or 3 DOE nuclear facility must establish, implement, and take actions consistent with a DOE-approved USQ procedure that meets the requirements of this section. (b) The contractor responsible for a new Hazard Category 1, 2, or 3 DOE nuclear facility must submit for DOE approval a procedure for its USQ process on a schedule that allows DOE approval in a safety evaluation report issued pursuant to § 830. 207(a) of this part. (c) The contractor responsible for a Hazard Category 1, 2, or 3 DOE nuclear facility must implement the DOE-approved USQ procedure in situations where there is a: (1) Temporary or permanent change in the facility as described in the existing documented safety analysis; (2) Temporary or permanent change in the procedures as described in the existing documented safety analysis; (3) Test or experiment not described in the existing documented safety analysis; or (4) Potential inadequacy of the documented safety analysis because the analysis potentially may not be bounding or may be otherwise inadequate. (d) A contractor responsible for a Hazard Category 1, 2, or 3 DOE nuclear facility must obtain DOE approval prior to taking any action determined to involve a USQ. (e) The contractor responsible for a Hazard Category 1, 2, or 3 DOE nuclear facility must annually provide to DOE a summary of the USQ determinations performed since the prior submittal. (f) If a contractor responsible for a Hazard Category 1,
official document · source cfr-2024 · id 10:§ 830.203