Planning, bidding, contracting, and constructing.
CFR · 2024-01-01 · US · Title 7
(a) (b) (1) State Director's and Rural Development engineer/architect's comments and recommendations, and if noncompetitive negotiation per § 1942.18(k)(4) is accepted by the Agency, submit an evaluation of previous work of the proposed construction firm. (2) Regional attorney's opinion and comments regarding the legal adequacy of the proposed procurement method and proposed contract documents. (3) Copy of owner's written request and description of the procurement method proposed. (4) Copy of the proposed contract. (c) (d)